A full bathroom remodel typically runs three to six weeks from demolition to final fixtures. Perhaps ten of those days involve anyone working in the room.

The sequence
Demolition — 1 to 2 days.
Rough-in — plumbing, electrical, framing, blocking. 2 to 4 days.
Inspection — booked, and nothing can be covered until it passes. Days.
Insulation and backer board — 1 to 2 days.
Waterproofing — 1 day to apply, then cure time before anything goes on it, usually a day or more depending on product and humidity.
Flood test — 24 hours, on a tiled pan.
Tile — 2 to 4 days, then grout the following day, then grout cure before sealing or use.
Drywall, tape, and paint — several days with drying between coats.
Fixtures and trim — 1 to 2 days.
Glass — measured after tile, then 1 to 3 weeks fabrication.
Final inspection.
Where the waiting is
Permits and inspections, which are scheduled rather than instant.
Cure times — membrane, mortar, grout, paint. These cannot be compressed and attempts to do so produce the failures that appear later.
The flood test, which is 24 hours well spent.
Glass fabrication, which cannot begin until the tile is done and which is often the longest single wait.
Material lead times, particularly for anything ordered rather than stocked. A back-ordered vanity stops the job at the end.
What actually causes overruns
Something found behind the wall. Rot, missing venting, corroded supply. It stops the schedule while a solution is priced and agreed.
Change orders, which restart the sequence for whatever they affect.
Materials arriving late, which is the most avoidable cause — have everything on site before demolition where possible.
A failed inspection, which stops work rather than slowing it.
Trade availability, since each specialist has other jobs and a gap of a few days between trades is normal.
Compressing it, honestly
The compressible parts are procurement and coordination, not cure times.
Order everything early and confirm it is on site before demolition. Choose in-stock tile. Order the glass configuration early so the glazier is ready to measure the day the tile is grouted. Book inspections as soon as the work qualifies.
Those four remove most of the avoidable delay. Nothing removes the cure times.
Living through it
For a single-bathroom house, the timeline is the cost. Worth agreeing at the outset: whether the toilet can be reinstated temporarily, whether the crew works consecutive days or in blocks, and what the realistic worst case is.
Contractors will usually accommodate a request to keep the toilet usable for part of the schedule if it is raised before the plan is set.
The unrealistic quote
A contractor quoting a full bathroom in a week is describing working days, not elapsed days, or is planning to skip cure times.
Ask them to walk through the sequence with dates. The answer either includes the waiting or it does not, and that tells you which kind of quote it is.
Seasonal effects
Contractors are busiest in spring and summer, and lead times to start are longest then. A bathroom booked in autumn frequently starts sooner and gets more consistent attention.
Cure times are also affected by conditions. High humidity slows paint and mortar; a cold unheated house slows everything. Both are worth mentioning if the work falls in an awkward season.
Keeping track
Ask for a written schedule with the sequence and the expected dates, and treat slippage in the early stages as a signal rather than noise — a rough-in that runs three days late usually means the whole schedule moves, because the trades behind it are booked elsewhere.
A weekly check-in of five minutes prevents most of the frustration that comes from not knowing what is happening.